45% on the report, 37% on site

How a 13-point gap between a subcontractor's claimed progress and the work actually built was caught before it reached a payment certificate on Çiftçi Towers.

On the Çiftçi Towers project (2016–2019), a ceramic subcontractor reported 45 percent progress on their work package and told our QA/QC team and the owner's representative that the package had been handed over.

On this tower, 45 percent meant ceramic work finished through the 16th floor. Our daily reports and weekly site walks told a different story: the crews were still working on floor 12.

We went back to site with the quality team and re-ran the checks against the NCR forms, including the ones already closed. The real numbers: 37 percent progress, and only 32 percent actually delivered and accepted. The payment for that package was recalculated and corrected before it went out.

I did not take the report at face value. I walked the floors myself and checked the paperwork against what was physically built. A 13-point gap between what was claimed and what was verified would have gone straight into a payment certificate if nobody had checked.

Do you verify progress claims against the physical work, or against the report on your desk?