T2 · Tool

Interim payment certificate (IPC)

Enter cumulative progress per BOQ item. This period's net payment is calculated after previous certificates, advance recovery, retention and VAT.

Sample data
ItemDescriptionContract amountPrevious %Cumulative %This periodProgress
A.01Ceramic and natural stone finishes (lobby, wet areas)$356,257 $53,439
A.02Gypsum board suspended ceiling incl. acoustic panels$415,634 $70,658
A.03Timber slat wall cladding$298,440 $74,610
A.04Internal doors, fire rated (EI60)$347,376 $69,475
A.05Bathroom fixtures and sanitaryware set$515,925 $128,981
A.06Glass balustrade with stainless handrail$317,089 $47,563
A.07Guest room FF&E (fixed joinery)$1,514,843 $151,484
A.08Paint and wallcovering$337,734 $60,792

Interim payment certificate no. 7

Cumulative work done (incl. VO)$1,553,301
Less previous certificates-$854,298
Gross work this period$699,002
Advance recovery (15%)-$104,850
Retention (5%)-$34,950
Net amount (excl. VAT)$559,202
VAT (20%)$111,840
Amount payable$671,042
Physical progress36.8%
Advance outstanding$382,500Total advance $615,495
Retention held$77,665Cap $207,265
Contract + VO$4,145,297From BOQ (excl. VAT)

Advance recovery continues until the full advance is repaid; retention stops once the cap is reached. These rules are modelled on FIDIC Sub-Clauses 14.2 and 14.3; check the particular conditions of your own contract.