Budget and profitability control

Enter budget, actual cost and estimate to complete per cost group. Earned value (EVM) indicators and margin are calculated automatically.

Sample data
Cost performance (CPI)0.89Critical
Schedule performance (SPI)0.89Critical
EAC (by CPI)$4,754,545Team forecast: $4,360,000
Planned margin13.0%Revenue $4,850,000
Forecast margin10.1%Difference -2.9 pts
Cost groupBudget (BAC)Actual (AC)To complete (ETC)At completion (EAC)VarianceStatus
$1,275,000-$25,000On budget
$675,000-$55,000Overrun
$800,000-$20,000Watch
$535,000$5,000On budget
$740,000-$20,000Watch
$335,000-$25,000Overrun
Total$4,220,000$2,615,000$1,745,000$4,360,000-$140,000

A CPI below 1.00 means each unit of money spent produces less than one unit of work. In this tool, below 0.95 is a warning and below 0.90 is critical.